General Contractor, Heavy Highway Construction, Utah: UDOT I-15; Springville to 400 South Interchange

July 18, 2011


Owner: Utah Department of Transportation

General Contractor: Utah County Constructors (UCC)
Staker Parson Companies joint venture with Wadsworth Brothers Construction

Completion Date: November 2009

Location: Springville, Utah

Staker Parson Companies and Wadsworth Brothers Construction teamed up as Utah County Constructors to complete this $73-million design-build contract with UDOT. The team reconstructed and widened two miles of SR-77. Utility systems were relocated and upgraded, a new overpass was constructed and the overpass over the railway at 400 West was removed and replaced.

UCC completed the project over 6 months ahead of UDOT’s required completion date.

  • 90,000 cubic yards excavation
  • 1 million tons imported fill material, completed in 11 months
  • 45,000 tons asphalt paving
  • 5,500 cubic yards concrete