US 40; Gusher East Bound Passing Lane & Center Turn Lane

Company

Burdick Materials

Project Type

Aggregates

Asphalt Paving

Location

Gusher

Owner: Utah Department of Transportation
General Contractor: Burdick Materials
Start Date: 10-18-2019
Completion Date: 10-05-2020
Subcontractors or Key Contractors: BHI, B&K, Coughlin Companies, 
Materials Used and Quantities: 

  • Granular Borrow = 79,000 Tons
  • Road Base = 37,000 Tons
  • HMA 26,475 TON 
  • SMA = 9,746 Tons 

This project included widening the existing US-40 through Gusher to include a center turn lane, additional eastbound passing lane, and acceleration/deceleration lanes at the major intersections. Burdick Materials added the center turn lane to improve safety through the town of Gusher. After widenings, the entire roadway was capped with SMA.

“

"This project will benefit the Uintah Basin for years to come by optimizing transportation for the traveling public along with helping to grow the economy and the oil industry. "

Troy Ostler - RE

CIVCO ENG.

“