ITD – US20-26, Locust Grove to Eagle Rd

Company

Idaho Materials & Construction

Project Type

Aggregates

Asphalt

Asphalt Paving

Highway

Location

Southern Idaho

Owner: ITD
General Contractor: Idaho Materials & Construction
Start Date: January 2020
Completion Date: December 2020
Subcontractors or Key Contractors: Boise River Fence, Chadez Concrete, Concrete Placing Co, Idaho Lines & Signs, Idaho Survey Group, KB Welding, Lawn Co, Milestone Construction, Porter Yett, Qualitree, Specialty Construction Supply, Strata and TEK-Solutions.

Materials Used on Project and Quantities:

  • Granular Subbase – 55,130 Tons
  • ¾” Aggregate Base – 27,200 Tons
  • Superpave HMA SP-3 – 19,670 Tons
  • Topsoil – 3,435 CY

Work of adding additional westbound and eastbound lanes between MP 39.22 and 40.22, US 20/26, Chinden Blvd, Locust Grove to Eagle Road, traffic signal modifications at Locust Grove and Eagle Rd, as well as pedestrian and irrigation improvements through this portion of the corridor. This project had major coordination between HOA’s and the improvements of their frontage properties.