LCC Early Action (Little Cottonwood Canyon)

Company

Staker Parson Materials & Construction

Project Type

Asphalt

Excavation

Location

South Wasatch Front

Owner: UDOT Region 3 
General Contractor: Staker Parson 
Start Date: May 2020 
Completion Date:   Nov 2020 
Subcontractors or Key Contractors:  B. Jackson Engineering & Construction, B & K Construction, Premier Striping INC, Geneva Rock Products

 

On one of the most dangerous and busiest highways in the State of Utah, US-6, Staker Parson Materials & Construction was able to safely mill & overlay the highway stretch during the night hours from May to September 2020. Working within a 9-hour nightly mill and overlay shift, our traffic control, trucking, asphalt plant, and construction crews were successfully able to rotomill 4″ of existing asphalt and pave back 2.5″ of hot mix asphalt (HMA). Upon completing the HMA phase of 28,134 tons, we paved back 18,553 tons of Stone Matrix Asphalt (SMA) on 17 lane miles, with only two bumps to grind.

 

Materials Used & Quantities: 

  • 28,134 tons of 12.5mm PG 64- 34 75 Gyro (25% RAP W/ Lime) HMA 
  • 18,553 tons of 12.5mm PG 70- 28 W/ Lime of Stone Matrix Asphalt (SMA) 
  • Chip Seal Coat, Lightweight 251,269 square yard 
  • Rotomilling – 4 Inch 220,621 square yard 
  • Micro-Surfacing – 52,348 square yard