Red Ledges Development
Company
Reynolds Excavation
Project Type
Construction
Location
South Wasatch Front
Owner: Red Ledges Land Development
General Contractor: Reynolds Excavation
Start Date: 2011
Completion Date: 2015
Materials Used and Quantities:
- Sewer Line 6”-10”: 24,500 LF (self-performed)
- Storm Drainage Pipe 12” – 24”: 14,000 LF (self-performed)
- Waterline 8” – 24”: 33400 LF (self-performed)
- Aggregates: 85,000 Tons
- Asphalt Paving: 10,000 Tons
- Mass Grading: 120,000 Cubic Yards
- Pressure Reducing Vaults- 5
- Water Booster Pump Station
Construction of new roads and infrastructure at Red Ledges in Heber City, UT. Large quantities of pipe were installed along with mass grading and paving on steep mountain terrain. Several pressure-reducing vaults were installed along with a large pump station. All work was self-performed for the project.