SR-39

Company

Staker Parson Materials & Construction

Project Type

Asphalt

Asphalt Paving

Location

North Wasatch Front

Owner: UDOT
General Contractor: Staker Parson Materials & Construction
Subcontractors or Key Contractors: Rower Construction, AAA Barricade, and A-Core
Materials Used on Project and Quantities:

  • 16,150 ton 3/8” HMA
  • 2,333 CY Light Weight Chips

The project was on SR-39 on the east side of Monte Cristo to Woodruff. Crews started with several soft spot repairs and had to mill and pave before A-Core could pre-grind the surface. The team overlaid 16,150 tons of HMA just short of 12 miles at 1.5” deep while Rower Construction replaced a cattle guard in the middle of the project. Our chip seal crew chipped the entire 12 miles. AAA Barricade did all our traffic control with a pilot car operation.