US-91; North Smithfield to Idaho

Company

Staker Parson Materials & Construction

Project Type

Asphalt

Construction

Highway

Location

North Wasatch Front

Owner: UDOT
General Contractor: Staker Parson Materials & Construction
Materials Used on Project and Quantities:

  • 500 Tons of HMA
  • 6,100 tons of Type C chips
  • 780 tons LMCRS-2
  • 225 tons of CSS-1

The project is located on US-91 in the north end of Cache Valley, from Smithfield, Utah, to the Idaho border, approximately 10.64 miles. Crews are performing lane leveling and providing a paved turnout for snowplows to safety turnaround at the Idaho border. In addition, crews will apply approximately 490,000 square yards of Utah Department of Travel (UDOT) Type 2 chip seal to the roadway surface along with new pavement markings. The project duration is 40 days.