Vineyard 6MG Water Tank
Company
Jack B. Parson Ready Mix Concrete
Project Type
Ready Mix Concrete
Location
South Wasatch Front
Owner: Orem City
General Contractor: Dry Creek
Start Date: September 21, 2022
Completion Date: Fall 2022
Materials Used on Project and Quantities:
- 870 cubic yards of concrete
On September 21, 20222, Jack B. Parson performed night work, pouring 870 cubic yards of concrete and establishing the floor of the new Vineyard City 6MG Water Tank project. Crews were able to pump an average of 120 cubic yards per hour by utilizing two pumps.
Vineyard City is a small but fast-growing community on the east side of Utah Lake in Utah County. This water tank will serve as an additional water resource for the area and surrounding communities.